Major construction at Ballinger Park Waterfront in Mountlake Terrace this summer

Wednesday, June 30, 2021

Ballinger Park Waterfront to close for construction July 1 and 2 (reopens July 3-5) and then closes from July 6 through September. 


Plus side: new fishing pier, boat dock, boat launch, enhanced shoreline improvements, and accessible pathway from the Senior Center coming!

Photo courtesy Dean Wallace Photo, LLC


Construction of the Ballinger Park Waterfront Project begins on Thursday, July 1 and Friday, July 2, closing specific areas of the waterfront area in order to begin work on major park improvements.

The waterfront will temporarily reopen July 3-5, for the holiday weekend, with the closure resuming on July 6 and continuing into September.

The waterfront project will add a new fishing pier, boat dock, boat launch, and enhanced shoreline improvements. Project funding also covers the new restrooms at the boat launch as well as an accessible pathway from the Senior/Community Center to the boat launch area. 

Demolition of the existing fishing pier, boat ramp, and tire rip rap is another component of the work. The total project cost is nearly $1.5 million.

What will be closed? The boat launch, driveway, and parking lot area. Additionally, there will be no access to existing fishing pier or wading area during construction.

Why close the beach and fishing area during the summer? The project is reliant upon federal permits that stipulate in-water work can only be done during the fish window period of July 1 through August 31. The in-water construction work will occur in July and August, and upland work will conclude in the month of September.

The remainder of the 55-acre park will be open and available to the public. Alternate access for small hand launch boats will be located only on the east side of the park and is marked on site. 

Parking will only be available at the north parking lot near the Senior Center at 23000 Lakeview Drive.

“We understand it is disappointing that the beach will be closed for most of the summer,” stated Recreation and Parks Director Jeff Betz. “However getting funding for these terrific amenities that were included in the 2015 Ballinger Park Master Plan is a huge win not only for Mountlake Terrace, but the region.”

To learn more about Ballinger Park projects, visit www.cityofmlt.com/2042 
 
For more information about this project, contact Recreation and Parks Director Jeff Betz at jbetz@mltwa.gov or 425-640-3101



0 comments:

Post a Comment

We encourage the thoughtful sharing of information and ideas. We expect comments to be civil and respectful, with no personal attacks or offensive language. We reserve the right to delete any comment.

ShorelineAreaNews.com
Facebook: Shoreline Area News
Twitter: @ShorelineArea
Daily Email edition (don't forget to respond to the Follow.it email)

  © Blogger template The Professional Template II by Ourblogtemplates.com 2009

Back to TOP