Op-Ed: Sound Transit bus lane through LFP would deforest Bothell Way and shift the road west into 110 properties

Saturday, March 4, 2023

CORE is a group of concerned neighbors who live in LFP, sharing information about ST3 and its impacts on our community. Contact: info@lfpcore.org or see www.lfpcore.org
----


Lake Forest Park prides itself on its mature trees and green entry along Bothell Way, SR 522, its central transit corridor. This contributes to the city’s character as a green village. 

These trees and our environment, the very identity of Lake Forest Park, are at threat. 


Sound Transit plans to construct a 1.2-mile, dedicated eastbound bus lane through Lake Forest Park as part of their SR522/145th BRT (bus rapid transit) project. 

This will remove 490 trees, deforesting Bothell Way in the city. Also, it will widen the road, shifting it west, cutting into the properties of 110 residents. 

Tall concrete retaining walls, requiring extensive road construction, will be built to support the new steep cuts. This will destroy the character of Lake Forest Park, turning our city entry into a concrete corridor. 

NE 165th Before - A green village
NE 165th After - A concrete corridor

Luckily, there is a better way and it is not too late to spare our city’s trees and environment while still achieving important regional transit goals.

We are a small community of nearly 14,000 residents. Many of us live here because we value a close relationship with nature. 

Sound Transit has avoided providing community transparency, meaningful analysis, and meaningful community outreach during their design process for the SR522/145th BRT project in Lake Forest Park. 
This project, currently at the 60% design stage, could have serious negative consequences on our community. We ask Sound Transit to modify the design, reducing impacts and costs.

Between 2019 and June 2020, Sound Transit dramatically changed the alignment, shifting Bothell Way to the west, implementing the “West Shift.” This shift impacts 110 property owners and the greater Lake Forest Park Community. 

Sound Transit never informed us of the magnitude of this shift or the impacts created by this “West Shift.” The “West Shift” changes the character of our community, affecting residential housing disproportionately.

Sound Transit has focused solely on creating a Business Access and Transit (BAT) lane, disregarding all other factors. Their plan does not address the concerns of our community. 

Nor does it consider the most likely alternative to the BAT lane: Queue Jumps. Queue Jumps are dedicated lanes and signal priority at busy intersections that allow transit to get a head start on traffic. Sound Transit designed Queue Jumps for NE 145th Street, where Seattle prohibited BAT lanes. 


We ask Sound Transit to modify the design and compare the cost and efficiency of Queue Jumps to the dedicated BAT lane. This will substantially reduce the amount of tree removals, the need for walls, property acquisitions, and overall cost. Queue jumps would achieve nearly the same transit time savings, which with the BAT build, is only 2.3 minutes during the three-hour, eastbound, afternoon rush hour.

The current plan removes 490 trees along the alignment, deforesting Bothell Way. With this expansion, the highway moves approximately 10’-12’ closer to the west side homes, removing the landscaping from 60,000 square feet of our neighbors’ backyards. 

There is no plan for noise mitigation. Instead, on the west side of Bothell Way, there are concrete retaining walls, up to 16’ tall, along nearly the length of the alignment. These retaining walls create a concrete corridor that will send sound up these faces and also eastward, across the highway. On the new sidewalk next to the highway, the sound will exceed 80 decibels.

Buses will run every 10 minutes, up and down both sides of Bothell Way, totaling 220 trips daily. 


Sound Transit’s SR522 Noise and Vibration Study did not sample sound along the alignment at the most impacted residential areas. In fact, the report was completed before the “West Shift.” Also, an outside agency never completed an Environmental Impact Statement, as typically required by Washington State.

Sound Transit’s plan for widening the highway on the east side of Bothell Way shows that at Bsche’tla creek, the steep banks of the creek and the buffer zones are “cleared and grubbed,” removing over 28 trees, clearing the understory, making this slide-prone area more unstable. 

This construction impacts habitat and nearby businesses, requiring even more property acquisitions on the east side of Bothell Way, south of 155th Street NE.

Regarding budget, this project has the most expensive cost per mile in ST3. The price tag for ST3 ranges from $626 million to $651 million. Of the 205 total property acquisitions, 110 are in Lake Forest Park. 

Sound Transit budgeted $83 million for the property acquisition costs in LFP. The overall cost for SR522 / NE 145 BRT is over $250 million, or 40% of the total ST3 budget.

We support transit. 

We request a more equitable, environmentally healthy, sustainable, and contextual design that we can all be proud of when this Project is completed and it becomes our legacy for the next 100 years. The best way to achieve these goals is to modify Sound Transit’s current plan utilizing queue jumps instead of a dedicated eastbound BAT lane.

What You Can Do:


8 comments:

Anonymous,  March 4, 2023 at 8:08 AM  

How is this good for the environment?

Anonymous,  March 4, 2023 at 11:07 AM  

Funny how the average homeowner has to jump hoops and pay massive permit fees to do any work around a tree, but, developers can cut down swaths of forest. We need to stop cutting down our local trees and learn to work around it.

Anonymous,  March 4, 2023 at 12:38 PM  

Please see the recent Seattle Times Article on March 2nd, written by Daniel Beekman, Seattle Times staff reporter. He quotes an assessment by Seattle’s Office of Sustainability and Environment. "Seattle’s tree canopy is slowly declining at a time when we need more canopy to mitigate the effects of climate change and build community health and resilience." The assessment recommends more planting, better care for existing trees and new regulations for developers. This is a great read and I recommend it to you for a better understanding of environmental concerns.

Anonymous,  March 4, 2023 at 4:54 PM  

Looking on google earth street view, it looks like the area they’re trying to save is overrun with invasive blackberry and ivy. Maybe it’ll be good for this project to happen bananas it’ll also remove a ton of invasive plants. This op-ed reeks of NIMBYism. They pretend to care about the trees to halt much needed development (and my guess is they’ll probably improve surface water infrastructure with this project too), but you can also clearly see from street view that many of the people living on these properties have topped their trees (probably for view of Lake WA).

Anonymous,  March 4, 2023 at 6:57 PM  

I think the whole point of the article is that it isn't. But then again the world has, what, billions of trees? How much does chopping down a handful really impact the planet? Insignificantly. But it's Seattle, so people be crazy.

But do you want to sit in traffic forever on a highway somewhere burning fossil fuels and exhausting them into the air because there isn't a better way to get there?

Anonymous,  March 4, 2023 at 8:09 PM  

I mean really, do we really need to go into the environmental impact of removing native trees ? They were left there for for a reason. in 19640 ish, when that freeway was built, they were planted as a buffer between the freeway and the homes, to diffuse carbon monoxide and sound. And yes I can back that up my parents bought their home in 1940 when I 5 was a freaking dirt road. I have pictures. Back then King county was a lot smarter. I mean seriously, 2023 King county, can you not do something more productive with a damn tax money than this? By the way who is complaining? Or are they just wanting to spend money to freaking spend money??

Anonymous,  June 28, 2023 at 7:40 PM  

Seattle metropolitan area should take advantage of all of its water ways and canals with the new technology wake-less high speed water taxis that could zip large numbers of commuters all over the region for a fraction of the cost.

https://www.youtube.com/watch?v=PuVgYtMfy-A

Anonymous,  January 30, 2024 at 6:28 PM  

I was wondering what was taking a regional transit investment so long to get done. Sure enough, someone doesn't want some trees cut down in their backyard. SR522 like every other state road or highway is owned by all the residents of the state, not just the communities they pass through. Queue jumps are not remotely effective in heavy traffic, create a pinch point, and make a BRT system worthless. Let LFP keep it's 80 year old highway configuration and trees (we all love trees), and just scrap the S3 Stride project (save the money). Or, we should build it through another city who understands that a regional transportation system that works in a metro area that has almost 4 million people means our roads won't look the same as they did in 1950. I would like to live on an Island full of trees as much as anyone, but everyone needs roads that are built to handle the traffic of today and a transit system built with speed and reliability. A third option was suggested by a transit group that proposed the state simply take one of the two existing general purpose lanes through LFP and convert it to a BAT, with no expansion necessary (or permission needed). One general purpose in each direction, that would really make it feel like 1950!

Post a Comment

We encourage the thoughtful sharing of information and ideas. We expect comments to be civil and respectful, with no personal attacks or offensive language. We reserve the right to delete any comment.

ShorelineAreaNews.com
Facebook: Shoreline Area News
Twitter: @ShorelineArea
Daily Email edition (don't forget to respond to the Follow.it email)

  © Blogger template The Professional Template II by Ourblogtemplates.com 2009

Back to TOP