Showing posts with label sidewalks. Show all posts
Showing posts with label sidewalks. Show all posts

Long-term sidewalk closure in front of Kenmore Park-and-Ride

Tuesday, October 27, 2026


The work area has been extended to include part of the west driveway at the Kenmore Park-and-Ride. Driveway access will be maintained. The pedestrian detour route has been updated to include a pathway through the east parking lot to get around the work, see updated map below.

September 28 through December 2026
Work hours: Monday–Friday, 6 a.m.–3 p.m.

Starting Monday, September 28, Sound Transit will close the sidewalk in front of the Kenmore Park-and-Ride’s east parking lot for Stride S3 Line construction. Crews will work Monday through Friday, 6am –3pm. Crews need to close the sidewalk in front of the east parking lot to complete a variety of construction activities including utility, roadway improvements, and building a landscaping strip.


Pedestrians must follow the detour routes 24/7 to get around the sidewalk closure (see map).
  • Eastbound pedestrians:
    • Pedestrians will be able to access the Kenmore Park and Ride and bus stops via the northern sidewalk and will not need to follow the detour.
    • Pedestrians looking to access anything east of the Kenmore Park and Ride will detour via 73rd Ave NE and SR 522 (Bothell Way NE) to get to the Burke-Gilman Trail, then return via 77th Ave NE.
  • Westbound pedestrians:
    • Pedestrians looking to access the Kenmore Park and Ride or anything west of it will need to detour via 77th Ave NE and SR 522 (Bothell Way NE) to get to the Burke-Gilman Trail, then return via 73rd Ave NE.
The Kenmore Park-and-Ride will remain open and accessible. The King County Metro bus stop next to the work zone is not affected by the work. Drivers, cyclists, and pedestrians should follow posted signs and plan for extra travel time.

 

Read more...

Join a community workshop to improve walking and biking near light rail stations February 10 and 11, 2026

Friday, January 23, 2026


Join our community workshops and help us plan where new sidewalks and bike lanes should go.

Shoreline South / 148th Station workshop
February 10, 2026 from 7-8:30pm

Shoreline North / 185th Station workshop
February 11, 2026 from 7-8:30pm


Read more...

Learn about the Dayton Ave sidewalk project at open house May 6, 2025

Saturday, May 3, 2025


Big changes are coming to Dayton Ave N, and we want you to be a part of it! 

Please join us on Tuesday, May 6, 2025, for a Project Open House to learn more about the upcoming new sidewalks project along Dayton Avenue N, between NW Richmond Beach Road and N 178th Court.

đź“… Date: Tuesday, May 6, 2025
đź•– Time: 7:00pm (Presentation begins at 7:15 p.m.)
📍 Location: Richmond Highlands Recreation Center, 16554 Fremont Avenue N, Shoreline

This is a great opportunity for residents, pedestrians, cyclists, and anyone who travels through this corridor to get involved and share their thoughts on the proposed improvements. This project will bring a new sidewalk to one side of Dayton Avenue N. The goal is to create a safer, more accessible route for everyone—whether walking the dog, biking to work, or pushing a stroller.

Whether you walk, bike, drive, or live along Dayton Avenue N, this project will shape how your community moves and connects. We hope to see you there!

Learn more here

Read more...

Dayton sidewalk project public meeting and online open house

Friday, April 18, 2025

The new sidewalk will run along the west side of Dayton 
from Richmond Beach Road and N 178th Court.

Tuesday, May 6, 2025 from 7-8pm with presentation at 7:15pm

Join the City of Shoreline and your neighbors to learn more about the new sidewalk project coming to Dayton Avenue N and give us your thoughts on design options!

This project will construct a new sidewalk on Dayton Avenue N between NW Richmond Beach Road and N 178th Court. The sidewalk will be built on the west side of the street.

Project improvements include:
  • Sidewalks with curbs and gutters
  • Bicycle facilities
  • Curb ramps and other Americans with Disabilities Act (ADA) improvements
  • Crosswalks
  • Drainage improvements
Can’t join us? Visit our Online Open House between May 6 – May 20.

Project website

Project Manager Zahid Khan, zkhan@shorelinewa.gov

Read more...

Open house for 19th Ave NE new sidewalk project December 17, 2024 - in person and online

Wednesday, December 11, 2024

19th Avenue NE new sidewalk project: Open house

A new sidewalk is coming to 19th Ave NE from NE 196th St to NE 205th St! 

Join the City of Shoreline and your neighbors to learn more about the project's early design and arborist’s report and ask questions and provide comments.

Project Design Open House

In person

Online
If you are unable to make it to the open house on the 17th, there will be an opportunity to leave comments and ask questions during our online open house. Go to shorelinewa.gov/19avesidewalk after December 17 to find a link to the online open house.

Project Overview


The 19th Ave NE Sidewalk Project will construct sidewalk on the west side of 19th Ave NE and sidewalk and curb ramp improvements at the major intersections between NE 196th St and NE 205th St /244th St SW.

This project is part of the 2018 voter-approved effort to build and repair sidewalks throughout Shoreline.

Project Timeline 
  • Preliminary Design: Winter 2024
  • Final Design: Early 2025
  • Construction: Summer 2025
Project information
Project Manager Zahid Khan

Read more...

Shoreline and Lake Forest Park take different routes to pedestrian safety

Wednesday, October 30, 2024


Last year was the deadliest year on record for pedestrians. Comparing the budgets for Shoreline and Lake Forest Park’s shows differing strategies for addressing pedestrian safety.

Fueled by tens of millions of dollars in grants, Shoreline plans to spend $96 million on pedestrian projects while Lake Forest Park - facing a $3 million deficit - turns to automated cameras to slow speeders and curb reckless drivers.

Area roads are more dangerous than ever. According to Shoreline’s annual Traffic Report, the number of pedestrian crashes hit a record high last year and the Washington Traffic Safety Commission says more pedestrians were killed in Washington State last year than in any other year on record.

Out of Lake Forest Park’s $7.5 million transportation fund, $7 million will be spent to build a roundabout at the intersection of Ballinger Way (SR 104) and 40th Place NE. 

The city received grants from the state to pay for half of the roundabout. Studies have shown roundabouts improve safety for pedestrians. The city also plans to spend another $200,000 from the transportation fund to design and construct wheelchair accessible sidewalk ramps. 

A map from the levy LFP voters rejected in 2021 shows the locations of possible pedestrian safety projects

But with the city expecting to end the 2025-2026 biennium with a $3 million deficit, Lake Forest Park has turned to automated traffic safety cameras to slow speeders and transform dangerous roads into safe streets for pedestrians. 

The city first deployed traffic cameras in 2009 and now operates red light cameras on Bothell Way and speed cameras at its two elementary schools. Revenue from those cameras are expected to generate $4,381,800 in revenue for the city’s general fund.

A new state law allowed the city to leave the cameras at Brookside elementary on 178th Street turned on year-round and all-day, even when school is not in session. After the city turned on the traffic cameras on 178th all day in June, average speeds dropped from over 30 mph to less than 25 miles per hour. 

At an August 5 city council meeting, Lake Forest Park Mayor Tom French said, 
“the average speed in the 178th zone prior to the installation of the 24/7 traffic cameras was over 30 miles an hour.”
After 60 days, “it is down now to 24.3 miles an hour. It's below 25 miles an hour, so by any metric it has been an enormous success,” he said.

According to the city’s budget, the new traffic cameras on 178th will generate over $8 million in revenue over the next two years. 

But the new state law requires the city to spend those funds on traffic safety improvements after paying operating costs (the city was previously allowed to deposit the revenue into the general fund). 

The budget does not say which traffic safety projects the city will fund with the millions of dollars it expects to collect. A levy for parks and sidewalks that LFP voters rejected in 2021 would have collected about $2 million annually to pay for a network of sidewalks across the city - especially near schools. 

Unlike neighboring cities, Shoreline has resisted adoption of traffic cameras and earlier this year, parents from Meridian Park Elementary brought a petition with 180 signatures asking the Shoreline city council to install speed cameras on 175th street in front of Shoreline’s largest elementary school. 

Instead, the city will spend tens of millions of dollars on infrastructure. Shoreline’s proposed Capital Improvement Plan names $95,956,157 worth of “Pedestrian / Non-Motorized Projects” over the next six years, accounting for roughly 30% of its $321,138,986 total transportation budget. 

A map from Shoreline’s Transportation Improvement Plan shows the locations of funded and unfunded projects. 

One third of Shoreline’s revenue for capital projects will come from federal and state grants.

In total, the city plans to spend $87,235,306 (mostly from state and federal grants) on the 145th Street Corridor from the light rail station east of I-5 to Linden west of Aurora.

The project will widen the roadway to add accessible shared-use paths to replace the existing narrow strips of pavement.

The city will spend $39,012,986 to build the 148th Non-Motorized Bridge over the next two years with more than 98% of that coming from regional, county, state and federal grants.

In 2018, a ballot measure approved by Shoreline voters raised sales tax by 0.2% to pay for 12 new sidewalks and the city council increased vehicle license fees by $20 to fix existing sidewalks that are unsafe and inaccessible to people using wheelchairs. 

According to the budget, over the next two years the city plans to spend revenue from the sales tax on sidewalks for Meridian Ave N, Westminster Way N, 19th Ave NE, Dayton Ave, Linden Ave, and 8th Ave NW.

Bike lanes on Meridian funded with a $630,180 federal grant are planned and Shoreline will begin painting a series of sharrows on side streets that the city calls the westside Off-Corridor Bike Network. 

Next year the city will spend $184,000 on a study of a possible off-corridor bike network on the east side of I-5.

The city will spend $500,000 to study the proposed Trail Along the Rail project - a 2.5 mile shared-use trail roughly parallel to the light rail line running north-south through Shoreline.

The first phase of the 175th Street project will begin in 2026 but no pedestrian improvements are planned in the next two years. 

The city will spend $23.3 million to rebuild 175th between meridian and I-5 to reduce the chances that the road collapses during an earthquake which could sever a major arterial and destroy sewer lines. 

The city says later phases of the project will benefit pedestrians, but those phases are still being debated and have no estimated dates. 

According to the budget, the cost of the 175th project could exceed $90 million and extend beyond 2030. 

The Shoreline city council will hold public hearings and discuss the proposed budget, property taxes, fees, and capital improvement plan on November 4 and 18. 

The Lake Forest Park city council will hold a final public hearing on the proposed budget and property taxes on November 7.



Read more...

Shoreline satisfaction survey: residents want city to address homelessness and build sidewalks

Thursday, September 12, 2024

By Oliver Moffat

At the Monday, September 9 meeting, the Shoreline city council reviewed results of the 2024 resident satisfaction survey - which the city conducts every two years.

Residents expressed high satisfaction with the city and its parks but gave the city low marks for dining, entertainment, sidewalks and its response to homelessness.


A chart from the resident satisfaction survey compares Shoreline with other cities in the US and Northwest

Most residents (89%) said Shoreline was an “excellent” or “good” place to live - far higher than the US and Northwest average of 49%. Survey respondents have for decades rated Shoreline favorably on this question with 91% in 2014 and 87% in 2004.

Of all city services, residents (again) rated the overall quality of parks and recreation most favorably with 81% saying they were satisfied. Shoreline residents rate our parks much higher compared to other cities in the US (48%) and Northwest (49%). Resident satisfaction with parks hasn’t changed much over the years with 82% satisfied in 2014 and 79% in 2004.

Satisfaction rating rebounded significantly since the 2022 survey conducted during the COVID era - with 56 of 71 questions showing improvements.

But with only 23% saying they were satisfied, residents were most dissatisfied with Shoreline as a place for dining and entertainment. 

And residents say dining and entertainment options are getting worse in Shoreline. Ten years ago, in 2014, 29% of residents were satisfied with dining and entertainment and when the city first asked the question in 2012, 30% were satisfied. Even during COVID lockdowns residents rated the city higher with 27% satisfied in 2022.

When asked about transportation and land use, 53% of residents said they were dissatisfied with the availability of sidewalks in their neighborhood. Notably, residents are less satisfied with sidewalk availability now than they were in 2014 when 47% were dissatisfied and in 2004 when only 41% were dissatisfied.

A map from the resident satisfaction survey shows opinions about sidewalks in Shoreline neighborhoods

In 2018, voters approved a sales tax increase to pay for new sidewalks. As part of the ballot measure, twelve locations were identified for new sidewalks across the city but the city estimates those projects won’t be completed until 2029.

Of all city services, residents were (again) most dissatisfied with Shoreline’s “overall response to homelessness” with only 30% saying they were satisfied. And 50% of residents said the city should do more to address homelessness - more than any other city service.

A chart from the satisfaction survey shows residents want the city to address homelessness

In 2020 and again in 2022, residents also told the city that addressing homelessness should be its top priority and residents rated the city’s response to homelessness as the service they were most dissatisfied with.

Despite repeated resident requests for the city to take action on homelessness, in April, the Shoreline council approved a housing and human services plan that recommended the city instead “Maintain Current Level of Service” while city staff continue to study the problem.


Read more...

8th Ave NW new sidewalk project online open house

Wednesday, July 31, 2024

A typical cross section of the street after the project is completed will include two 10 foot traffic lanes, a 5 foot bike lane, and a 6 foot sidewalk.

Visit the online open house
Dates: Open through August 12

We're planning a new sidewalk on 8th Ave NW and want to hear your suggestions and questions. You can add your thoughts to an ideas board or pin them directly to a map of the project area. Please tell us what you think!

Project Overview

This project will construct a new sidewalk on 8th Ave NW between NW Richmond Beach Road and NW 180th Street near the north side of Sunset Park. The sidewalk will be built on the east side of the street. A bike lane will be added to the west side of the street.

This project is part of the 2018 voter-approved effort to build and repair sidewalks throughout Shoreline.

Project improvements include:
  • Pedestrian facilities with curbs and gutters
  • Bicycle facilities
  • Curb ramps
  • Drainage improvements
Project website


Read more...

8th Ave Sidewalk Open House July 23, 2024

Monday, July 15, 2024

Tuesday, July 23, 6:30 pm


First Lutheran Church of Richmond Beach
Upper Room (elevator accessible)
18354 8th Avenue NW
Shoreline, Washington 98177

Project design open house: We are designing a new sidewalk coming to 8th Avenue NW from NW 180th Street to Richmond Beach Road NW. Join the City of Shoreline and your neighbors to learn more about the project and give us your thoughts on the early design.

Project Details
  • New sidewalk with curbs and gutters on the east side of the street
  • Bicycle lanes
  • Curb ramps
  • Drainage improvements
  • Project Timeline
  • Preliminary Design: Summer 2024
  • Final Design: Winter 2024/2025
  • Construction: Spring/Summer 2025
More information Project webpage

Project Manager Zahid Khan, PE
zkhan@shorelinewa.gov, 206-801-2486


Read more...

No easy solution to Shoreline’s 175th problems

Tuesday, May 21, 2024

More than fifty activists with Save Shoreline Trees and Tree Action Seattle rallied on 175th against the city’s plan to expand sidewalks and add bike lanes that could remove more than 274 trees
Photo by Oliver Moffat

By Oliver Moffat

175th is a problem with no easy solutions. Traffic jams and crashes are back to pre-pandemic levels and an earthquake could send the road into Ronald Bog. Metro’s new 333 bus is coming soon to the road. The city wants people to walk and bike more but pedestrians (including students) must brave crossing up to seven lanes of traffic. 

Activists want the city to narrow sidewalks to save trees and businesses have fought road diets in the past. Whatever happens, everyone in the region will be impacted for decades to come.

An arial photo shows the 75 foot crosswalk at the intersection of Meridian and 175th where pedestrians must brave five lanes of car traffic in all directions

On Sunday, May 19, 2024 more than fifty activists with Save Shoreline Trees and Tree Action Seattle turned out for a rally on 175th to protest the City's plan to widen 175th between Aurora and I-5 to make room for pedestrians and bicyclists which could cost over $88 million and require chopping down 274 trees.

With traffic jammed (as usual) on 175th street, passing drivers honked enthusiastically, showing their support for the activists’ calls to save trees by narrowing the proposed sidewalks.

Shoreline city council member Keith Scully even stopped by to show his support.

Flyers distributed by Save Shoreline Trees called on the city to reduce sidewalks to 7 feet or less and said 13 foot sidewalks are unnecessary. The group said they don’t want 175th to be “devastated” like 145th where the city removed more than 300 trees to make way for sidewalks and roundabouts to support the light rail station opening later this year.

Trees increase walkability by providing shade and mitigate urban heat islands caused by large expanses of pavement, according Sandy Shettler from Tree Action Seattle. “Walkability includes shade. These are the public’s trees and they should be saved for the good of public health” she said while waving to passing cars.

A map from the Washington State Patrol Collision Analysis Tool shows the locations of ten years of crashes along 175th between Aurora and I-5 

Plagued by traffic jams, N 175th Street between I-5 and Aurora is Shoreline’s busiest city street with more than 20,000 vehicle trips per day. It’s also one of the city’s most dangerous roads. According to data from the Washington State Patrol, collisions on N 175th Street have roared back to pre-pandemic levels: in 2019 there were 77 crashes; in 2023 there were 76.

Starting in 2019, the city collected feedback from over 1,500 residents to list their top priorities for 175th street: pedestrian walkability, solving traffic jams, and improving safety were the top three priorities. 

Although the city didn’t ask specifically about tree preservation, “landscaping character” was rated at the bottom of the wishlist just above bike lanes by Shoreline residents.

To address traffic jams, the city won’t be able to make the road much wider - it’s already a five-lane road and is over 75 feet wide. It narrows to four lanes at Wallingford where it squeezes between rock retaining walls and spreads out to seven lanes at Aurora. Because of the phenomenon known as Induced Demand, adding more lanes probably wouldn’t help.

But traffic jams are just the start of the problems. When the city started designing the project, they discovered an earthquake could cause 175th to “slip and slide” into nearby Ronald Bog and received an $8 million grant from FEMA to rebuild the road.

Flyers distributed by Save Shoreline Tree called 175th “a primary access route to I-5 and a truck route” and said because there was no light rail station, wider sidewalks weren’t necessary. But later this year, Metro’s new route 333 will provide frequent, cross-town bus service along 175th street, increasing pedestrian traffic on the road.

The city’s Transportation Element Bicycle Plan, adopted by the city council in 2022, promises bike lanes on 175th street that would be safe enough for children to ride on.

At the rally, Susanne Tsoming, co-chair of Save Shoreline Trees, when asked about the city’s plan said, “It’s a major arterial and not made for strolling… I think it’s insane to ride a bike on this road with cars.”

Parents and students, who must brave five lanes of car traffic to get to Meridian Park elementary, want the city council to do something about traffic safety on 175th. Between I-5 and Aurora there are only seven crosswalks and the road can be up to 90 feet wide.

The location of trees to be removed to make way for sidewalks and a bike lane near Meridian Park elementary are shown on a map from the arborist report 

The city’s Climate Action Plan says vehicles are the largest source of greenhouse gas emissions in Shoreline and sets a goal to get more people to ride busses and bikes. Shoreline’s Complete Streets policy requires road projects to be designed for the safe and convenient access of all users including pedestrians, bicyclists and transit users; not just motorists.

On the other side of town, the city’s Transportation Improvement Plan calls for a road diet on the east side of I-5 that (instead of expanding the width of the road) would shrink NE 175th St from four lanes to three while adding bike lanes. 

A table shows the number of car lanes and widths of the seven crosswalks pedestrians must brave while crossing 175th street between Aurora and I-5.
That plan would cost about $2.3 million without removing trees. Although the U.S. Department of Transportation says road diets improve safety and calm traffic, twenty years ago the city council rolled back a plan to put 15th Ave NE in the North City business district on a road diet after push back from businesses.

On May 20, the city council was scheduled to vote on adoption of the Transportation Improvement Plan. And the council was scheduled to discuss a plan to roll out Scooter and Bike Sharing in the city. The Natural Environment and Transportation sections of the Comprehensive Plan were also on the agenda.

UPDATE: At the June 3rd city council meeting, the 175th street project will be back on the agenda for discussion.

A presentation from Save Shoreline Trees is no longer on the agenda. In an email, Kathleen Russell from Save Shoreline Trees said, “Although the City initially approved our application for a presentation, we are not in agreement on the guidelines and we have withdrawn our application.” 

On June 10, the much anticipated (and overdue) Annual Traffic Report will be reviewed by the city council and Traffic Enforcement Cameras will be discussed. The council will vote on whether to add Scooters and Bicycle Sharing to Shoreline’s roads.

On June 24, before the council adjourns for their summer vacation, the Commute Trip Reduction Plan will be reviewed.

5-23-2024 Save Shoreline Trees will not be making a presentation at the June 3rd council meeting.


Read more...

Shoreline’s Climate Action Plan: fewer cars; more trees and sidewalks

Saturday, May 18, 2024

A graph from the 2022 Climate Action Plan shows 56% of total greenhouse gas emissions in Shoreline come from transportation (mostly gasoline-powered vehicles).

By Oliver Moffat

On May 13, 2024 after hearing public comments from school children asking for safer streets, and tree activists calling for narrower sidewalks on 175th street, the city council reviewed how much progress was made on Shoreline’s Climate Action Plan.

The city’s first Climate Action Plan in 2013 set a goal to reduce emissions by 25% between 2009 and 2020; but by 2021, the city had reduced emissions by only about 6% for the entire decade.

In 2022, the city set a new goal to reduce emissions 60% between 2019 and 2030; meaning the city will need to reduce emission 6% per year on average for every year this decade.

The city also wants to reach net zero emissions by 2050 by offsetting all emissions with sequestration.

According to the city’s plan, Shoreline’s tree canopy covers 37% of the city and currently sequesters about 13,890 metric tons of CO2 each year; while Shoreline’s cars emit ten times that much CO2 each year: 139,782 metric tons.

At 56% of the total, by far the largest source of greenhouse gas emissions in Shoreline comes from transportation (mostly gasoline-powered vehicles).

Getting people to give up their cars will require safe sidewalks and bike lanes that people actually want to use, so the city’s plan lays out a long list of actions to make the city more walkable and bike-able.

But adding sidewalks and bike lanes on 145th street while preserving the wide, five-lane road for cars has required removing trees - angering tree activists who are now calling for narrowing the proposed sidewalk on 175th to save trees.

Councilmember John Ramsdell
Photo courtesy City of Shoreline 
Councilmembers Scully, Pobee and Ademasu promised more trees would be preserved on 175th street; councilmember John Ramsdell highlighted the challenges of balancing tree preservation with the need to get people out of their cars.

“Believe me, I love trees,” he said, “But I think there’s a really important statistic to be aware of: … a mature tree can absorb about 48 pounds of carbon dioxide per year. 
"If we can remove one car from using our roads… according to the EPA, a typical car emits 4.6 metric tons of carbon dioxide per year. That’s over 10,000 pounds of carbon dioxide greenhouse gasses per year.”

Read more...

Stop the Chop rally Sunday by Ronald Bog

Friday, May 17, 2024

 Photo by Kean Engie

Join the “Stop the Chop” rally on Sunday, May 19, 2024 at 1pm at Ronald Bog Park to call attention to the City's plans to remove trees along N 175th between Stone Way N and I-5 for the N 175th Corridor Project.

Some of the trees to be cut are marked with
orange ribbons. Photo by Kean Engie.
Volunteers from Save Shoreline Trees have tied an orange ribbon on many of the 274 trees along N 175th identified in the December 2022 draft arborist report to be removed.

The public is invited to join the "Stop the Chop" rally, and bring your own sign, or “write a note to a tree” at this event.

Save Shoreline Trees agrees safety for all is a top priority.

However, for the sake of climate resilience and emergency, we ask the Council to reconsider the design for N 175th Corridor Project. 

This project is scheduled to be discussed by Council on June 3, 2024.

Volunteers with Tree Action Seattle will host a “write a note to a tree” table on Sunday.

Ronald Bog Park is located at 2301 N 175th St, just east of Meridian Ave N.

Update: Photos by Kean Engie. "Write a note to a tree" table on Sunday.

Read more...

Where the sidewalks end on 180th street

Sunday, May 12, 2024

A photo by Kevin Atkinson, Treasurer, North City Neighborhood Association,
shows a pedestrian walking in the street where the sidewalk ends on 180th

By Oliver Moffat

On the 2nd Thursday of each month, the North City Neighborhood Association hosts a meetup at Monka Brewing Company to talk about local issues and make friends.

When the neighbors meet, one topic that is sure to come up is traffic safety. And the section of road that comes up most frequently is where the sidewalks end on 180th street in North City.

A map by Mark Notermann, Co-Chair of the North City Neighborhood Association, shows the location of apartments and condos (yellow), the light rail station (red), recently completed sidewalks (green), and unfunded sidewalk projects (blue) 

Whether walking, biking, driving or taking the bus, 180th is the primary road residents of apartments in the neighborhood will take to reach the 185th street station.

There are two particularly troubling gaps in the sidewalk along NE 180th Street between 15th Ave NE and 12th Ave NE that force pedestrians to walk in the roadway.

A photo shows where pedestrians must use the road on 180th street 

That section of 180th is on a hill with poor visibility. And that block of 180th is the location of a school bus stop, the fire station, and later this year Metro’s 348 will add frequent all-day and all-night service to the street.

A map shows the locations where the sidewalks end on 180th street
forcing pedestrians into the road 

The city includes 180th in the estimated $80 million worth of road improvements for the 185th Street Multimodal Corridor Strategy.

But given staffing shortages and funding constraints, the city says it could be more than a decade before the 185th project would get the green light.

A map shows the five segments of the 185th Street Multimodal Corridor Strategy with estimated costs; North City residents have raised safety concerns about segment “E” - 180th between 15th and 10th

The city’s proposed Transportation Improvement Plan breaks the 185th project into five different segments labeled “A” through “E”.

Section “E” would build sidewalks on 180th between 10th and 15th and would cost about $5 million.

But the section that North City residents are most concerned about is between 12th and 15th - which might be much less expensive.

A photo by Kevin Atkinson, Treasurer, North City Neighborhood Association,
shows a wheelchair user on 180th

North City residents have asked the city to separate the west-side and east-side segments of the 185th project in the Transportation Improvement Plan.

Separating segments “D” and “E” would be consistent with the 145th and 175th corridor projects and would allow city engineers to consider the priority and costs of the North City segments separately from the west-side segments.

On May 20, 2024 the Shoreline city council will vote on adoption of the Six-Year Transportation Improvement Plan.


Read more...
ShorelineAreaNews.com
Facebook: Shoreline Area News
Twitter: @ShorelineArea
Daily Email edition (don't forget to respond to the Follow.it email)

  © Blogger template The Professional Template II by Ourblogtemplates.com 2009

Back to TOP