Construction resumes October 28, 2026 near SR 104 Lyon Creek fish passage site

Tuesday, October 27, 2026


Construction will resume Wednesday, October 28, 2026 near the SR 104 Lyon Creek fish passage site for removal of a buried storage tank. Construction will happen from 7am to 3:30pm for about five weekdays. Work will not happen overnight or during weekends.

During working hours, one lane of NE 185th Street will close at the intersection of SR 104. Signed detours will guide people around the closure.

Underground tank removal

During this project, our contractor found a buried fuel storage tank on site that was not previously identified in plans. The tank was discovered midway through construction, after known fuel tanks had already been safely removed.

In recent months, we have worked with the property owner and developed a plan to remove the tank, which is located near the intersection of NE 185th Street and 35th Avenue NE. This storage tank, which is believed to be empty, must be removed.

Our contractor will use industry best practices to remove this final tank and any potentially contaminated soils nearby. Contaminated soils removed from the work zone during tank removal will be disposed of at authorized facilities. Crews will fill around the tank with clean soils and add landscaping before finalizing construction.


Read more...

Seattle City Light Night Work – SR 104 Roundabout Project

Saturday, October 3, 2026


Seattle City Light Night Work – SR 104 Roundabout Project
Project Update: October 2, 2026

Seattle City Light will begin nighttime utility work this weekend that is expected to continue through Wednesday of next week in support of the City of Lake Forest Park SR 104 Roundabout Project.

Crews will temporarily relocate high-voltage power lines to provide the necessary clearance for construction equipment and allow upcoming SR 104 Roundabout Project construction activities to  proceed safely.

Nearby residents may notice nighttime utility vehicles, construction equipment, work lighting, intermittent noise, and temporary traffic-control measures. Drivers should use caution and follow posted signs and directions through the work area.

The City recognizes the inconvenience associated with nighttime construction and appreciates the community’s patience while this important safety-related utility work is completed. Updates will be provided if the schedule or anticipated impacts change.

Project Contact

Mike Read, PE | Senior Project Manager
City of Lake Forest Park | 17425 Ballinger Way NE
mread@cityoflfp.gov | 206-957-2836 | Cell 206-666-7565


Read more...

Ballinger Way Roundabout Project Update: Temporary Utility Relocations

Tuesday, September 22, 2026


Temporary Utility Relocations to Support Retaining Wall Construction - September 21, 2026

The City of Lake Forest Park advises residents that retaining wall construction for the SR 104 / NE 40th Place Roundabout Project begins today. To facilitate this work, temporary relocations of overhead electrical and communication lines are scheduled for the week of September 28, 2026.

The City is coordinating these activities with Seattle City Light, Comcast, and Lumen to support construction progress while minimizing potential service disruptions to nearby properties.

Anticipated Service Impacts

Widespread service outages are not anticipated. However, a limited number of individual homes may experience a temporary interruption in electrical or communication service during the relocation work. Residents with planned service interruptions will be notified directly by the appropriate utility provider or project representative.

If an unexpected electrical outage occurs, residents should contact Seattle City Light for outage assistance. For interruptions to internet, telephone, or cable service, residents should contact their respective communications providers.


Read more...

Water District says no health concerns with discolored water

Sunday, September 13, 2026


The Ballinger Way NE Roundabout construction has required the District to temporarily change how water flows through portions of our distribution system. The impacts of these changes, particularly discolored water in some areas, have been greater than we anticipated.

We also recognize that our communication with customers regarding these changes and their potential impacts has not been adequate, and we apologize. As additional shutdowns or system changes are required, we will do a better job of providing advance notice to impacted customers, including information about what to expect and how to prepare.

Changes in water flow can disturb naturally occurring minerals such as calcium and iron within water mains and cause temporary discoloration. There is no health concern associated with the discoloration. Out of an abundance of caution, the District collected water samples from representative locations in the distribution system and all bacteriological samples came back negative.

We have also been in communication with the Washington State Department of Health, Office of Drinking Water regarding the situation and our response.

Discolored water?

If you experience discolored water, run cold water from a bathtub, outside faucet, or other high-flow fixture for 5–10 minutes. If the discoloration persists, contact the District at 206-365-3211 or office@lfpwd.org.

Alan Kerley
General Manager
LFP Water District

Read more...

Lake Forest Park Water District Notice

Wednesday, September 9, 2026

LFP roundabout project Ballinger & 40th Pl NE
Photo by David Carlos

Lake Forest Park residents: Are you experiencing low water pressure or discolored water?

The Lake Forest Park Water District completed the first scheduled water shutdown related to the Ballinger Way NE Roundabout construction. A few additional scheduled shutdowns will be needed as the project progresses, and customers will e-notified by the LFP Water District in advance.

During this time, some customers may notice slightly lower water pressure than normal and changes in water flow may also occasionally cause discolored water.

If you notice discoloration, run your cold water for a few minutes until it clears. The LFP Water District will also continue flushing as needed. There is no health concern associated with the discoloration.

For more information, please visit the Lake Forest Park Water District webpage.


Read more...

Update on LFP Roundabout project

Thursday, September 3, 2026

City of Lake Forest Park's SR 104 / 40th Place NE Roundabout Project is well underway.

Current Work Water main installation, retaining wall preparation, excavation, curb/sidewalk demolition, roadway work

Community Access Pedestrian, bicycle and emergency responder access will always be maintained, but Traffic Detours, temporary lane shifts and flagging operations will occur.
  • Reminder: SB 40th Place NE is closed N of SR104 through late November 2026 - NO vehicles other than construction personnel & equipment are allowed to travel in both directions on 40th Place NE.
  • NO vehicles other than emergency first responders are permitted to travel SB 40th Place NE to SR 104.
Work Hours 
Daytime construction activities (7:00am to 3:30pm)

Construction Timeline – September 2026
  • September 1–4 — Water main installation along 184th; Wall 2 pad preparation and installation.
  • September 3–4 — Mass excavation in front of Wall 2 location.
  • Week of Sept. 7 — Water main work along 40th, Wall 3 pad preparation, curb/sidewalk demolition, and water-main testing.
  • Week of September 21 – Structural support for Wall construction begins.
What Residents Can Expect
  • Active construction equipment in the corridor.
  • Temporary traffic control and intermittent lane shifts.
  • Safe pedestrian routes maintained.
  • Bicycle accommodations maintained.
  • Emergency responder access maintained at all times.
  • Retaining wall, water main, excavation, and roadway-related work progressing through the corridor.
  • Dust control and erosion protection measures throughout construction.
Frequently Asked Questions

Will the road stay open? 
  • Yes. Traffic will be maintained with temporary control measures.
Can I still walk or bike through the area? 
  • Yes. Pedestrian and bicycle accommodations will remain available.
Will emergency vehicles have access? 
  • Yes. Emergency responder access will always be maintained.
What major work is planned in September? 
  • Water main installation, retaining wall preparation, excavation, curb/sidewalk demolition, and related roadway work are scheduled through mid-September.
Stay Connected

More information at QR code





Read more...

More about roundabouts

Tuesday, September 1, 2026


Multi-lane roundabout? Choose your lane before you enter.

A key difference with multi-lane roundabouts is that you need to pick the right lane before you enter.

As you approach:
  • Slow down and look for signs and pavement markings.
  • Choose your lane based on where you’re going.
  • Yield to all traffic already in the roundabout, including vehicles in the inside lane that might be exiting.
  • Enter when there is a safe gap.
Once you’re inside the roundabout, don’t stop or switch lanes. Keep going and use your turn signal when you’re ready to exit.

Remember, signs and pavement markings are there to help you. Follow them instead of making a last-minute lane change.



Read more...
ShorelineAreaNews.com
Facebook: Shoreline Area News
Twitter: @ShorelineArea
Daily Email edition (don't forget to respond to the Follow.it email)

  © Blogger template The Professional Template II by Ourblogtemplates.com 2009

Back to TOP