Work progressing on Ballinger Way roundabout

Monday, August 17, 2026


As promised, work began on the 40th Pl NE & Ballinger Way / SR 104 roundabout on August 3, 2026. 

As of August 16, the trees have been cleared on the corners.


The center island has been removed and the orange vinyl fencing installed.

The roundabout is a project of the City of Lake Forest Park. This new roundabout will include a single-lane roundabout, new sidewalks, shared-use pathways, four pedestrian crossings with refuge islands, and improved street lighting.

Next week the contractors will begin work on the water mains.

-Photos by David Carlos


0 comments:

Post a Comment

We encourage the thoughtful sharing of information and ideas. We expect comments to be civil and respectful, with no personal attacks or offensive language. We reserve the right to delete any comment.

ShorelineAreaNews.com
Facebook: Shoreline Area News
Twitter: @ShorelineArea
Daily Email edition (don't forget to respond to the Follow.it email)

  © Blogger template The Professional Template II by Ourblogtemplates.com 2009

Back to TOP