All lanes on SR 104/Ballinger Way expected to reopen Friday, November 7, 2025

Sunday, October 26, 2025

Fish culvert progress as of October 26, 2025
Photo by David Carlos

All lanes on SR 104 / Ballinger Way are expected to reopen Friday, November 7, 2025.

Construction is largely complete on the new fish passage built to carry Lyon Creek beneath SR 104. We are still finalizing earthwork around the culvert, finishing driveway and sidewalk work and preparing for final paving – which requires dry weather.

However, challenges remain with the underground sewer work happening adjacent to the new culvert. Underground utility work is inherently difficult, and sandy, silty soils in this area have compounded those challenges and slowed the pace of construction.

Planning to reopen Ballinger Way / SR 104 by November 7, 2025
Photo by David Carlos

We know this extended closure has created challenges for people who live, work and commute through this area. We also know these extensions are frustrating.

We expect our contractor will work 24 hours a day until this phase of work is finished, and if we can reopen SR 104 before November 7, we will.

Casey Conley
Construction communications
WSDOT Northwest Region


2 comments:

Anonymous,  October 26, 2025 at 3:32 PM  

"Paving requires dry weather, so let's schedule this project for the beginning of the wet season."

Anonymous,  October 27, 2025 at 12:53 AM  

Yup. This is why we can’t have nice things.

Post a Comment

We encourage the thoughtful sharing of information and ideas. We expect comments to be civil and respectful, with no personal attacks or offensive language. We reserve the right to delete any comment.

ShorelineAreaNews.com
Facebook: Shoreline Area News
Twitter: @ShorelineArea
Daily Email edition (don't forget to respond to the Follow.it email)

  © Blogger template The Professional Template II by Ourblogtemplates.com 2009

Back to TOP