Shorecrest construction update
Saturday, May 18, 2013
![]() |
| Looking to the southeast at the new main academic building at Shorecrest. Photo courtesy Shoreline Schools |
SHORECREST - construction update
GYM
Final punch list items (additional painting, etc.) to be completed over summer break.
THEATER
Final punch list items (additional painting, etc.) to be completed over summer break.
![]() |
| View of the north exterior walls of the new main academic building at Shorecrest. Photo courtesy Shoreline Schools |
MAIN ACADEMIC BUILDING
The building is expected to be completed in February 2014.
West Wing:
- Installation is under way of interior metal stud wall framing on first floor.
- Exterior masonry veneer installation continues along south wall; veneer installation to begin along north wall.
- Mechanical and Electrical rough-in to continue at first floor.
- Window installation to continue at second and third floor levels.
- Installation of insulation to continue at exterior walls at second and third floor levels.
- Commence installation of gypsum wallboard at interior walls at second and third floor levels.
Middle Wing:
- Electrical and plumbing rough-in continues at all levels.
- HVAC ductwork installation to continue at second and third floor areas.
- Interior steel stud wall framing continues at all levels.
- Underground electrical installation to commence.
- Concrete floor slab pours scheduled for second and third floor areas at north end.
East Wing:
- Preparation of sub-grade material at main floor level for slab pour to continue.
- Exterior metal stud wall framing to commence at third floor level.
- HVAC ductwork installation to begin.
- Concrete floor slab pours scheduled for second and third floor areas.
SITE
Completion of underground utilities and excavations for site concrete walls continues.