Project update: Lynnwood Link Extension

Thursday, March 29, 2018

Report to community 
from Sound Transit

Sound Transit continues to refine and finalize the design of the Lynnwood Link Extension track and stations.

This is an ongoing effort with input and collaboration from multiple partner agencies, engineers, contractors and artists.

Last year, cost estimates to complete construction of the Lynnwood Link Extension were higher than planned. The project team worked with its partner agencies to find potential design refinements that will help reduce costs while maintaining the project scale and scope:
  • 8.5 miles of Link light rail service between Northgate and Lynnwood
  • 4 stations: Northeast 145th Street, Northeast 185th Street, Mountlake Terrance Transit Center and Lynnwood Transit Center

Stay tuned for upcoming informational forums this summer, where more details about the latest designs of each station will be shared as the project nears the 90 percent design milestone.

Work to secure federal funding

In addition to preparing for construction, we continue to work with our federal partners to secure $1.17 billion in Capital Investment Grant (CIG) funding from the Federal Transit Administration. Earlier this month, the agency submitted a formal Full Funding Grant Agreement application, kicking off a negotiation on a final agreement that we expect can be executed this summer.

While due diligence toward successful execution of this grant is ongoing, we received promising news last week that the President has signed a spending bill that includes funding for the CIG program. We will continue working with members of our Congressional delegation to advance our application.

Did you know?

Lynnwood Link will be gearing up for active pre-construction work throughout this year, with major work anticipated to start in late 2018. You can expect to receive project-wide updates about construction this fall. In the meantime, we are actively working with the cities of Seattle, Shoreline, Mountlake Terrace and Lynnwood to get ready for construction. You may receive more local information regarding preconstruction activities such as utility work, demolition, clearing, grading and permitting processes in your neighborhood.

Some of these activities include:
  • Plant salvage events
  • Property acquisition
  • Community meetings
  • Localized pre-construction activities, such as clearing and grading
  • Field work, including geotechnical borings and survey work
Looking ahead to the rest of 2018

Spring 2018
Design continues toward construction-ready plans

Summer 2018
Localized demolition
Informational forums in Shoreline, Mountlake Terrace, and Lynnwood
Design continues toward construction-ready plans

Late 2018
Construction begins

See entire project schedule »

Stay connected

Get project updates »

More information

Contact our outreach team at LynnwoodLink@soundtransit.org
24-hour construction hotline: 888-298-2395


1 comments:

DIGITAL FACE MEDIA April 1, 2018 at 9:18 AM  

Three years late, $500 million over budget and they haven't even turned one shovel of dirt. #CriminalEnterprise #GovtSucks

Post a Comment

We encourage the thoughtful sharing of information and ideas. We expect comments to be civil and respectful, with no personal attacks or offensive language. We reserve the right to delete any comment.

ShorelineAreaNews.com
Facebook: Shoreline Area News
Twitter: @ShorelineArea
Daily Email edition (don't forget to respond to the Follow.it email)

  © Blogger template The Professional Template II by Ourblogtemplates.com 2009

Back to TOP