Eastbound lane closures in Kenmore through Wednesday
Sunday, November 22, 2026
Eastbound lane closures in Kenmore started at 6pm on November 20, 2026 and will continue through 12pm on Wednesday, Nov. 25. During this time, crews will pour and cure the concrete bus pads next to Stride station platforms. Dates and times are subject to change due to inclement weather or unforeseen issues.
After the concrete bus pads are poured, crews will remove the eastbound general lane closure around work areas. The eastbound bus-only lane will remain closed through 12pm Wednesday, Nov. 25, to prevent cars and buses from driving over the concrete bus pads while they harden.
Traffic patterns will change during weekend construction. Buses will merge into general-purpose traffic lanes to bypass the work. Temporary bus stops will remain accessible. Drivers, cyclists, and pedestrians should follow posted signs and plan for extra travel time.
Riders and drivers will still be able to make right turns in and out of businesses and residences on SR 522 (NE Bothell Way) between 61st Ave NE and 73rd Ave NE. All businesses and residences will remain open and accessible.
Building road improvements is key to ensuring the Stride S3 Line buses can move through the route more quickly. This work will allow Sound Transit to deliver fast, frequent, and reliable rapid transit service along S3. For more information on Stride S3 bus service, visit the Stride webpage.