| Photo courtesy WSDOT |
In Bellingham, the SR 11/Chuckanut Drive slide closed the road in this iconic area between Oyster Dome trailhead and Chuckanut Manor for 58 days while WSDOT crews worked seven days a week towards reopening.
![]() |
| WSDOT crews on Chuckanut Drive |
Crews manually removed loose rock on the cliff face, and drilled in anchors to stabilize the slope.
In addition they removed 3,600+ tons of debris, including 15+ SUV-sized boulders, and replaced 125 feet of guardrail.
The road was reopened on June 19, 2025.