N 165th - N 185th Streets (Marshbank Construction)
This week, crews will:
- Pour sidewalks on N 182nd Street (weather-permitting); access will be maintained via a single lane.
- Grade for paving the center lanes on Aurora between N 165th and N 175th Streets and begin constructing the stamped concrete medians.
- Continue trenching on N 175th Street to install underground communications lines and begin to install stormwater systems; traffic will be reduced to one lane in the eastbound direction.
- Continue work on N 185th Street including grading and pouring sidewalks. Traffic may be reduced to one lane in each direction.
- Continue forming and pouring the retaining wall on Aurora north of N 185th Street. Access to Firlands Way will be intermittently closed from southbound Aurora.
- Pour driveways, sidewalks and curbs and install signal bases on the west side of Aurora north of N 175th Street (weather permitting).
N 185th - N 192nd Streets (Johansen Excavating)
This week, crews will:
- Continue retaining wall construction activities on the west side of Aurora near the Department of Licensing and Shoreline Park and Ride. This work may require periodic single lane closures on Aurora in the southbound direction and/or single lane closures on N 192nd Street in the eastbound direction.
- Complete underground utility vault installations.
- Continue digging the joint utility trench (JUT) and stormwater trench along the west side of Aurora between N 185th and N 192nd Streets.
- Remove and/or prune trees and shrubs along the corridor to create room for new underground utilities, curbs, sidewalks and rain gardens.
Check website for more construction information.