| Photo by Jerry Pickard |
Utility work is done and the final curbing is being installed this week. A test section of pervious surface concrete is scheduled for installation this week and asphalt roadway paving is scheduled for Saturday, December 19, 2015 (both weather permitting).
| Turn from NE 178th St. to NE 180th St Photo by Jerry Pickard |
Once paved, the road will be reopened to traffic, with or without lane-control flagging, depending on adjacent work such as sidewalk and electrical installations.
![]() |
| New sidewalk by Eagle Scout Park Photo by Jerry Pickard |
The remainder of the concrete sidewalks will be done soon, also weather permitting. This will leave placement of the pedestrian-actuated crossing signs, landscaping, mitigation replanting, and the punch list of completion items.
| Photo by Jerry Pickard |

Thank God. Seems like the construction has taken forever.
ReplyDelete