Kenmore street construction

Monday, November 30, 2015

Over the next couple weeks, the construction team will continue working on the south side of SR 522 in Kenmore during the day, including:

    Continuing trenching and installation of utility vaults,
    Continuing retaining wall work near 61st Ave NE, and
    Installing waterlines and fire hydrants.

The construction team plans to complete work on sidewalks along the north side of SR 522 near Bethany Bible Church and Passport Travel by mid-December, depending on weather.

North side of SR 522: The construction team plans to complete work on sidewalks along the north side of SR 522 near Bethany Bible Church and Passport Travel in mid-December, depending on weather.

61st Ave NE: 61st Ave NE remains closed between SR 522 and NE 175th St and is expected to remain closed for approximately four months depending on weather.

    The team will continue installing retaining walls near the 76 Gas Station.
    The Burke-Gilman Trail is currently detoured around the crossing at 61st Ave NE. Check out the detour page on our website for details about the protected Burke-Gilman Trail detour and pedestrian detour around the work at 61st Ave NE.

The project is on schedule to be completed in June 2016.




0 comments:

Post a Comment

We encourage the thoughtful sharing of information and ideas. We expect comments to be civil and respectful, with no personal attacks or offensive language. We reserve the right to delete any comment.

ShorelineAreaNews.com
Facebook: Shoreline Area News
Twitter: @ShorelineArea
Daily Email edition (don't forget to respond to the Follow.it email)

  © Blogger template The Professional Template II by Ourblogtemplates.com 2009

Back to TOP